Example Asbestos Removal Projects in Huntington Park

The seven example jobs below are set in Huntington Park, Maywood and Bell, from a 1920s bungalow to a six-unit building. Each one lists what was sampled, what came out, the work days and an estimated cost.

Sprayed ceiling texture removed from a front room before new wiring and lights

Example project

Home
1920s bungalow in Huntington Park with a sprayed texture over the plaster ceiling of the front room
Original request
Run new wiring and hang a new ceiling fixture with recessed lights around it
Testing
A Cal/OSHA-certified asbestos consultant samples the texture at three spots and the plaster beneath it
Found
Asbestos in the sprayed texture
Clear
The plaster beneath it
Area
About 180 sq ft of ceiling
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$2,000

Scope of work

Three samples, the South Coast Air Quality Management District notice, the front room sealed with air filters running, the texture soaked and scraped into bags, a HEPA clean and the haul. The clearance air test, the wiring and the ceiling finish are separate.

Project overview

In this example, the owner of a 1920s bungalow is rewiring the front room and adding recessed lights. The plaster ceiling was sprayed with a texture long after the house was built, and the electrician will be cutting into it in several places.

The texture tests positive and the plaster under it is clear. The abatement crew takes the texture off first, so the electrician cuts into a bare plaster ceiling.

The goal

The goal is a bare plaster ceiling, so the wiring and the new lights go in with nothing positive overhead.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the ceiling in three places.
  2. Before work The abatement contractor files the district notice online and the owner empties the room.
  3. Day one The room is sealed and the texture is soaked and scraped into bags.
  4. Day two The ceiling is wiped down and an independent consultant tests the air before the electrician starts.

Planning right

  • Empty the front room and take down the curtains.
  • Ask the electrician to start after the air results.
  • Plan where to sit and sleep for the two work days.
  • Keep the lab report with the electrical permit papers.

Get a free quoteMore about popcorn ceiling removal

Two flooring layers removed from a rented kitchen and dining area

Example project

Home
1950s rental house in Maywood with sheet vinyl laid over an older tile in the kitchen and dining area
Original request
Replace the floor between tenants
Testing
A Cal/OSHA-certified asbestos consultant samples the sheet vinyl, the tile beneath it and the mastic under each
Found
Asbestos in the lower tile and its black mastic
Clear
The sheet vinyl on top
Area
About 220 sq ft of floor
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$3,100

Scope of work

Samples of both layers, the district notice, the kitchen and dining area sealed with air filters running, the vinyl lifted and the tile and mastic removed wet, bagging and the haul. The clearance air test and the new floor are separate.

Project overview

In this example, the landlord of a rented 1950s house wants a new floor before the next tenant moves in. The owner-occupant provision does not reach a rental, because the owner must live there and do the work, and the job is over 100 square feet in any case.

The sheet vinyl on top is clear, but the older tile beneath it and its mastic test positive. The abatement crew takes both layers up while the house is empty, and the flooring installer starts on a bare subfloor.

The goal

The goal is a bare subfloor in an empty house, so the next floor goes down with no old mastic left under it.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples both layers with the house empty.
  2. Before work The contractor files the district notice online and the landlord holds the new floor order.
  3. Days one and two The area is sealed, the vinyl is lifted and the tile and mastic come up wet.
  4. Last An independent consultant tests the air, then the installer is released.

Planning right

  • Schedule the work for the days the house is empty.
  • Remove appliances and cabinet kick plates the day before.
  • Hold the new tenant’s move-in until the air results.
  • Keep the lab report with the property file.

Get a free quoteMore about floor tile and mastic removal

Pipe wrap taken out of a crawlspace under a bathroom before the remodel

Example project

Home
1950s house in Bell with a raised floor and a crawlspace under the bathroom
Original request
Remodel the bathroom and move the sink and tub lines
Testing
A Cal/OSHA-certified asbestos consultant samples the pipe wrap at three spots and the tape at its joints
Found
Asbestos in the wrap on the hot-water line
Clear
The wrap on the cold line and the tape
Area
About 35 ft of pipe
Timeline
Less than 100 square feet of asbestos-containing material removed, so no district notice, then one working day
Cost
$1,700

Scope of work

Plastic around the access hatch and the work area, the wrap removed wet and bagged, a cleanup and the haul. The survey, the clearance air test, the plumbing and the bathroom finishes are separate.

Project overview

In this example, a Bell family is remodeling the only bathroom of their 1950s house. The plumber will be moving the sink and tub lines, and the old pipes under the floor are wrapped in a white insulation.

The wrap on the hot-water line tests positive and the rest is clear. The abatement crew removes it from the crawlspace first, so the plumber works on bare pipe.

The goal

The goal is bare pipe under the bathroom, so the new plumbing is connected to lines with nothing positive left on them.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the wrap from the access hatch.
  2. Results The hot-water wrap is positive and the cold-line wrap is clear.
  3. Work day The hatch and the work area are sealed and the wrap is removed wet and bagged.
  4. Then The plumber starts on the new layout.

Planning right

  • Clear the area around the crawlspace hatch.
  • Tell the plumber the hot-water line is out first.
  • Use the other bathroom or a neighbor’s for the work day.
  • Keep the lab report with the remodel plans.

Get a free quoteMore about HVAC duct and pipe insulation removal

Ceiling texture and floor tile removed from a small retail suite

Example project

Home
Small retail suite in a 1950s one-story commercial building in Huntington Park, empty between tenants
Original request
Strip the suite so a new tenant can build it out
Testing
A Cal/OSHA-certified asbestos consultant samples the ceiling texture, the floor tile, its mastic and the wall compound
Found
Asbestos in the ceiling texture and the floor mastic
Clear
The floor tile and the wall compound
Area
About 190 sq ft of ceiling and 190 sq ft of floor
Timeline
Notice no later than 10 working days ahead, then three working days
Cost
$4,900

Scope of work

Samples of each material, the district notice, the suite sealed with air filters running, the ceiling texture and the mastic removed wet, bagging and the haul. The clearance air test and the build-out are separate.

Project overview

In this example, the owner of a small commercial building has an empty retail suite and a new tenant lined up. A commercial suite is not a residential single-unit dwelling, so the survey comes first whatever the size of the job.

The ceiling texture and the mastic under the floor tile test positive. The abatement crew clears both before the tenant’s contractor starts the build-out.

The goal

The goal is a stripped suite with the positive materials gone, so the tenant builds out on a clean shell.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the ceiling, the floor and the walls.
  2. Before work The contractor files the district notice online and the owner holds the keys for the crew.
  3. Days one to three The suite is sealed, the ceiling texture comes off wet and the mastic is removed.
  4. Last An independent consultant tests the air, then the tenant’s contractor takes over the suite.

Planning right

  • Remove shelving and fixtures before the crew arrives.
  • Tell the tenant’s contractor which materials were positive.
  • Keep the district notice and the lab report together.
  • Plan the new ceiling and floor for after the air results.

Get a free quoteMore about renovation and demolition abatement

Old tile and mastic removed from under bedroom carpet before new plank flooring

Example project

Home
1950s house in Huntington Park with wall-to-wall carpet in the back bedroom
Original request
Pull the carpet and lay plank flooring
Testing
A Cal/OSHA-certified asbestos consultant samples the tile under the carpet and the mastic at four spots
Found
Asbestos in the tile and the mastic
Area
About 140 sq ft of floor
Timeline
Notice no later than 10 working days ahead, then one working day
Cost
$2,400

Scope of work

Four samples, the district notice, the bedroom sealed with air filters running, the carpet and pad lifted, the tile and mastic removed wet, bagging and the haul. The clearance air test and the plank flooring are separate.

Project overview

In this example, the owners of a 1950s house are changing the back bedroom from carpet to plank flooring. When the corner of the carpet is lifted, an old tile is under it.

The tile and the mastic test positive. The abatement crew removes them in one day, and the flooring installer comes after the air results.

The goal

The goal is a bare subfloor with no tile or mastic left, so the plank flooring lies on a clean surface.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the tile at the lifted corner and under the closet.
  2. Before work The abatement contractor files the district notice online and the owners empty the room.
  3. Work day The room is sealed, the carpet and pad come up, and the tile and mastic are removed wet.
  4. Last An independent consultant tests the air, then the installer is booked.

Planning right

  • Move the bed and dresser out of the room.
  • Take the door off its hinges if it opens inward.
  • Order the plank flooring for after the air results.
  • Keep the lab report with the flooring receipt.

Get a free quoteMore about floor tile and mastic removal

A vacated apartment sampled before its remodel, one unit at a time

Example project

Home
1960s six-unit apartment building in Huntington Park, with the owner updating each unit as it empties
Original request
Know what is in each unit before it is opened, starting with the one that just emptied
Testing
A Cal/OSHA-certified asbestos consultant samples the ceiling texture, the kitchen and bath floors and the kitchen wall in the empty unit
Found
Asbestos in the ceiling texture and the kitchen floor mastic
Clear
The bath floor and the kitchen wall
Timeline
Samples, then lab results, then a short report
Estimated testing cost
$650

Scope of work

A visit by the consultant, a set of samples from the one empty unit, a lab result for each and a short report that marks the sample spots. The same visit repeats when the next unit empties. Removing the positive materials is priced on its own.

Project overview

In this example, the owner of a six-unit apartment building does not want to survey everything at once. A unit in an apartment building is not a residential single-unit dwelling, so each unit is sampled before its remodel, whatever the size of the job.

The first unit shows asbestos in the ceiling texture and the kitchen floor mastic, and the report marks where each sample came from. The abatement crew is booked for that unit, and the next unit gets its own visit when its tenant leaves.

The goal

The goal is a report for each unit, so every turnover starts from its own sample results.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the empty unit.
  2. Results The lab reports each sample, with the ceiling texture and kitchen mastic positive.
  3. Next The abatement crew is booked for that unit before the remodel crew.
  4. Then The next unit is sampled when it empties.

Planning right

  • Give the consultant the keys and the unit number.
  • Ask for each unit’s report to be kept separate.
  • Keep the remodel crew out until that unit’s materials are removed.
  • Tell remaining tenants which unit is being worked on.

Get a free quoteMore about asbestos testing and surveys

Patched plaster removed from the wall behind torn-out kitchen cabinets

Example project

Home
1930s house in Huntington Park with its original kitchen cabinets on a plaster wall
Original request
Tear out the cabinets and replace them with new ones
Testing
A Cal/OSHA-certified asbestos consultant samples the plaster, the patch compound and the backsplash adhesive
Found
Asbestos in the compound used to patch the plaster behind the upper cabinets
Clear
The base plaster and the backsplash adhesive
Area
About 60 sq ft of wall
Timeline
Less than 100 square feet of renovation, so no district notice, then one working day
Cost
$1,700

Scope of work

Plastic over the floor and counters, the patched strip removed wet from the wall, bagging, a cleanup and the haul. The survey, the cabinets, the clearance air test and the wall repair are separate.

Project overview

In this example, the owners of a 1930s house are replacing the kitchen cabinets. Behind the uppers the plaster has been patched several times over the years.

The survey rule does not reach less than 100 square feet of renovation in a single-unit house, yet the owners have the wall sampled first. The patch compound tests positive, so the abatement crew takes the patched strip out wet before the cabinet installer arrives.

The goal

The goal is a wall with the patched compound gone, so the new cabinets hang on a surface that has been sampled.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the wall behind the uppers.
  2. Results The patch compound is positive and the base plaster is clear.
  3. Work day The kitchen is sealed and the patched strip is removed wet and bagged.
  4. Then The cabinet installer starts after the cabinets are out.

Planning right

  • Empty the upper cabinets and take down shelves.
  • Mark where the new uppers will hang.
  • Keep the lab report with the cabinet order.
  • Plan the wall repair before the new cabinets arrive.

Get a free quoteMore about drywall, joint compound and plaster removal

Request a free asbestos removal quote